Case Study - VicTrack, Sunbury Electrification Project

Job: Sunbury Station Balustrade/ Handrail Upgrades

Description:

Mechcon was engaged to supply, fabricate and install metal work to the station upgrades on the Sunbury Electrification Project.

Sunbury and Diggers Rest required New Galvanised Handrails in and around the station including wheel chair ramps and car park areas. Sunbury Station required over 500 Lineal meters of kickrail to be installed on existing balustrade overpass structure.

New sections needed to be pre-fabricated then taken onsite and retro fitted to bring existing Balustrade and Handrailing up to correct AS 1428.1 requirements.

Overview:

Job: Sunbury Station Balustrade/ Handrail Upgrades.

Client: BMD Group

Date Project Commenced: May 2012

Duration of Scope: 3 Months

SPECIFICATION
Welding: AS1554   Fabrication: AS 1428.1
Materials: Mild Steel
Protective Coatings: Sand Blast AS 1627.4 Class 2.5 Coating: Hot Dip Galvanised.

Like this article?

Share on Facebook
Share on Twitter
Share on Linkdin
Share on Pinterest
Share via Email
Share on WhatsApp

Have a project you would like to talk about?